wheatland homepage banner

The Wheatland Wind Project (WWP) began development in 2007. It is located thirty kilometres southeast of the Town of Drumheller. The WWP received an Alberta Utilities Commission (AUC) approval for the 122.4 megawatt (MW) wind power plant and a permit and licence for the substation from the AUC in September 2018. Construction of the WWP will involve the installation of twenty-four (24) Siemens Gamesa 5.0 MW wind turbines, an underground collection system, access roads and the construction of a new collector substation (the Badlands Substation), an Operations and Maintenance building, and temporary laydown areas. The WWP will connect to Alberta’s electrical grid through an existing 138kV transmission line located within the project area, which is owned by ATCO Electric Ltd. Commercial operation of the WWP is anticipated to begin in Q4 of 2022. This map shows the details and locations of the project infrastructure.

WWP began project construction in September this year and has now concluded for 2021. As of November 2021, approximately 70% of roads and clearing of 80% of the turbine sites were successfully completed. Construction at the substation will continue into December and conclude for the holiday season. Construction activities will resume in March 2022 and is expected to be at its peak in July & August 2022. We are on track to meet a December 2022 completion date for the project.

WWLP continues to engage local landowners and stakeholders throughout the WWP’s construction process in a way that respects community member’s needs. We hosted our first virtual open house on October 13, 2021. The open house presentation is available here, which includes information on the project team, construction activities, construction schedule and timeline, as well as additional information on the Community Liaison Committee (CLC). We will be hosting another open house in the early summer of 2022. More detail will be provided on this website and posted in local newspaper next year.

If you have any questions or inquiries regarding the current construction activities, schedule or timeline, please send us an email at info@wheatlandwind.com. For any emergency related to the constructed areas over the wintering months, please contact our Construction Manager, Juergen Kraus: 204-941-9938 or jkraus@potentiarenewables.com. Alternatively, you can contact our Project Manager, Keaton Lever, as well for any construction emergencies over the winter: 647-248-7946 or klever@potentiarenewables.com

December 2021:
Construction concluded at the WWP for this year and planned civil and turbine site construction for 2021 were successfully completed. Construction will commence again in March 2022.

October 2021:
Construction began at the WWP. The first open house was hosted virtually on October 13, 2021, and the local community was updated with information on construction activities, schedule and timeline. The next open house is planned for the early summer of 2022.

September 2021:
On September 8, 2021, the Engineering, Procurement and Contracting (EPC) of the WWP hosted a vendor open house and job fair in Drumheller. The EPC, Skyflo, was recruiting local contractors, businesses and individuals whose services related to the construction of the wind project, and networked with local trades, supplier and workers to foster mutual beneficial relationships.

April 2021:
WWLP submitted an update to Alberta Environment & Parks (AEP) outlining the various changes made to the project, including turbine manufacturer and model, and revisions to the project layout. The Spring 2021 newsletter was also disseminated to the local community.

March 2020:
WWLP evaluated power purchase opportunities and turbine technology updates for the WWP. Consultation on the project continued through 2020.

September 2018:
The AUC granted approval to construct, own, and operate the WWP and the Badlands 981S Substation.

May 2018:
WWLP submitted amendments to the original application with an updated project layout.

May 2017:
WWLP submitted applications to the AUC to construct, own, and operate the power plant, substation, and interconnection infrastructure.

April 2016:
Potentia Renewables Inc. entered into a partnership with Greengate Power Corporation for the Wheatland Wind Project.

Proposed Whetland Site

Wheatland Wind Project LP (WWLP) and Wheatland Wind Project Ltd. are special purpose entities controlled by Potentia Renewables for the Wheatland Wind Project.

Potentia Renewables Inc. is a fully integrated developer, owner, and operator of renewable energy assets. It is owned by Power Sustainable Corporation, a subsidiary of Power Corporation Canada (TSX: POW). With operations in Canada, the US, and Latin America, Potentia has recently been awarded four large, contracted wind assets in Western Canada. Potentia’s construction plans for these sites represent more than 625 MW of wind power to come online over the next two years

By Mail

Wheatland Wind Project LP,
by its general partner Wheatland Wind Project Ltd.
Suite #124
100, 111-5 Ave SW
Calgary, AB T2P 3Y6

By Phone

Project Manager
647-248-7946